Operations at new Port of Veracruz set for 2018

11 January 2017

The Ministry of Communications and Transport (SCT) of Mexico has confirmed that by the end of 2018, the first phase of the new Port of Veracruz will begin operating on a commercial basis.

This phase will have a cargo handling capacity of about 66 million tonnes. By 2024, the terminal is expected to have a capacity of around 90 million tonnes.

The total construction of the project involves an investment of about US$1.4 billion, with 80% of the total funding coming from private companies. The scheme is undertaken as a public private partnership.

According to the SCT, this project will ultimately double Mexico’s operational capacity, raising it from 260 million tonnes to more than 520 million tonnes.

This story was first published in Spanish in International Construction’s sister magazine, Construcción Latinoamericana

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

CONNECT WITH THE TEAM
Andy Brown Editor, Editorial, UK - Wadhurst Tel: +44 (0) 1892 786224 E-mail: [email protected]
Neil Gerrard Senior Editor, Editorial, UK - Wadhurst Tel: +44 (0) 7355 092 771 E-mail: [email protected]
Catrin Jones Deputy Editor, Editorial, UK – Wadhurst Tel: +44 (0) 791 2298 133 E-mail: [email protected]
Eleanor Shefford Brand Manager Tel: +44 (0) 1892 786 236 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA