Robbins launches Double Shield in Nepal

By Catrin Jones22 November 2022

China Overseas Engineering Group Co. Ltd and China Railway No. 2 Engineering Group Co Ltd have launched a 6.4m diameter Robbins Double Shield TBM for a 13.1km headrace tunnel located in southern Nepal.

A Robbins TBM in Nepal (Photo: Robbins)

Robbins says that the tunnel is connected to a new 28.6MW surface powerhouse on the Marin River to alleviate the shortage of power supply in the area. It will also be used for farmland irrigation in the districts of Dhanusha, Mahottari, Sarlahi, Rauthat, and Bara in the Terai Plain, diverting water from the Sunkoshi River to the Marin River. 

The headrace tunnel, for Sunkoshi Marin Diversion Multipurpose Project (SMDMP), is being bored through granitic rock with maximum overburden of 1,320m. 

The machine was customised for the conditions of a major fault zone 4km into the tunnel, says Liu Fengfan, Project Manager for contractor B-2/COVEC. He adds, “The TBM shield is a tapered design to reduce the risk of becoming stuck in squeezing ground; there is an enclosed cutterhead design to reduce the collapse of surrounding rock as well.

“The TBM has overcut capabilities and a high thrust. It has also been designed to be equipped with an extra high torque cutter head drive, as well as strong auxiliary thrust to be used in squeezing ground or weak fault zones to keep the machine from becoming stuck.”

MAGAZINE
NEWSLETTER
Delivered directly to your inbox, Construction Europe Newsletter features the pick of the breaking news stories, product launches, show reports and more from KHL's world-class editorial team.
More News from Construction Europe
Colas launches waste recycling network
The company aim to reduce the production of recycled materials by 50% by 2026
Case to stop construction sales in China
CNH Industrial will stop selling construction equipment in China from next year
EU could seize €300bn from Russia to rebuild Ukraine
The damage suffered by Ukraine is estimated at €600 billion
CONNECT WITH THE TEAM
Mike Hayes Editor, Construction Europe Tel: +44 (0)1892 786 231 E-mail: mike.hayes@khl.com
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: simon.kelly@khl.com
CONNECT WITH SOCIAL MEDIA